Key Takeaways
- Sector: Digital Infrastructure, Artificial Intelligence (AI).
- Geography: United States.
Analysis
A former cryptocurrency mining operation in Spartanburg County, South Carolina, is undergoing a significant transformation into a substantial Artificial Intelligence data center. AIB Data Centers, a firm specializing in digital infrastructure for AI and high-performance computing, is spearheading the redevelopment of its 16-acre site. This strategic pivot aims to capitalize on the escalating demand for AI-driven computing power, repurposing existing infrastructure for a more future-proof application.
The newly envisioned facility, designated as CLT1, will feature a dedicated data center building replacing the previous modular setup. A critical component of this project is a long-term agreement with Nebius, an Amsterdam-based AI cloud provider. This partnership secures 50MW of critical IT capacity for Nebius, underscoring the growing need for specialized AI infrastructure in Europe and beyond. The initial lease commitment spans 12 years, with provisions for two five-year extensions, signaling a robust, long-term commitment from the tenant.
Supporting this significant power requirement, the campus has secured a substantial 65MW utility supply agreement, extending for 15 years. AIB Data Centers projects the delivery of two 25MW data halls by the fourth quarter of 2027. While the company anticipates a financing mix involving customer prepayments, project debt, and preferred equity, the final project financing is still pending. This timeline highlights the urgency in the AI infrastructure sector, where "time-to-power" is frequently cited as a major bottleneck.
This development proceeds amidst a one-year moratorium on new data centers imposed by Spartanburg County in September. However, the project benefits from an exemption clause within the ordinance. This exemption applies to qualifying facilities of up to 65MW IT capacity located in designated industrial zones or on former industrial sites, provided they do not generate electricity beyond emergency backup. The proposed AIB agreement explicitly states the project's adherence to these conditions, capping its IT capacity at 50MW and the total facility at 65MW.
The initiative represents a significant economic injection into the region, with an anticipated $1.2 billion in investment from both AIB Data Centers and Nebius. The company's proposed commitments include a minimum of $400 million in capital expenditure, the creation of at least 28 full-time jobs, and substantial community benefit payments totaling $12.6 million over the initial lease term. This substantial investment underscores the economic potential of the AI sector for local communities.
Notably, AIB Data Centers, formerly known as BlockchAIn Digital Infrastructure, had already begun planning the site's repurposing before the county's moratorium. The company's existing 40MW crypto hosting operation was de-energized in June due to unfavorable Bitcoin market conditions, paving the way for this AI-focused transition. The leadership of AIB Data Centers, including CEO Jerry Tang, also heads TigerDC, a firm that previously withdrew a much larger $3 billion project proposal in the same county earlier this year after incentive negotiations failed. This prior experience may inform AIB's current approach to local engagement and development agreements.